In 2026 a single storey extension in London costs about £2,800 to £4,500 per square metre to build before VAT, or £3,360 to £5,400 with VAT at 20 per cent, rising to £4,000 to £5,500 (£4,800 to £6,600 with VAT) in inner London. A typical 25 m² rear extension at mid specification comes to around £90,000 to £105,000 including VAT. On top of that, allow £7,000 to £15,000 for the costs before work starts and a contingency of 10 to 15 per cent.

Almost everyone who books a call with us asks the cost question first. This page sets out how we price a house, what the money went on in our own recent cost plans, and the rates we use to check them, so that when we speak we can start from your house rather than from averages.

How do we work out your number?

We price your house line by line, from the drawings, in a construction estimating database of contractor and material rates. Each room is measured and priced in the order a builder would build it, so the demolition, the structure, the windows, the wiring, the plastering, the flooring and the decoration, at the rates a capable London builder tenders at. Then we go through every line against the drawings and take out anything that does not belong to your job.

A per square metre rate is only the sense check at the end. On the two cost plans we finished this autumn, the line by line figure came in 10 to 15 per cent under our own published rates, which is why we do not quote from the rate alone.

What you get is the cost by package, before and after VAT, so you can see what each part of the work costs and decide what to build now and what can wait. It also lists plainly what is not yet priced, such as the contingency, the fees and anything waiting on the structural engineer.

What does the money go on in a London house?

This autumn we priced the renovation of a house in north-east London that had stood unoccupied for more than two years. The family wanted the ground floor opened to the garden with a new sun room, the bathrooms brought upstairs, a timber framed rear dormer at first floor, a new roof, and a heat pump in place of the old boiler. These are the biggest packages from the cost plan.

Package

Ex VAT

With VAT at 20 per cent

Kitchen and utility

about £43,500

about £52,300

First floor rear dormer, structure and cladding

about £42,300

about £50,700

Living and dining rooms, including fitted joinery

about £36,200

about £43,500

Bathrooms (family bathroom, en-suite and WC)

about £31,800

about £38,100

Sun room

about £27,400

about £32,800

Main and rear roof

about £14,500

about £17,400

Heat pump and hot water cylinder

about £11,300

about £13,600

Site set-up and scaffold

about £8,500

about £10,200

House in total, before options

about £280,700

about £336,900

Two things stood out on this job. The trades that touch every room add up quietly, and plastering and decoration across the house came to about £37,700 before VAT between them, more than the sun room. And because the house had been unoccupied for over two years, which the council confirmed, the building work could be charged at 5 per cent VAT instead of 20. On this house that was worth about £42,000.

How much does an extension cost per square metre in London?

These are the rates we publish in our London borough guides and use to check our own cost plans. They are build costs for a good standard of finish in 2026, and exclude professional fees.

Type of work

Per m² before VAT

Per m² with VAT at 20 per cent

Single storey rear extension, outer and middle London

£2,800 to £4,500

£3,360 to £5,400

Single storey rear extension, inner London

£4,000 to £5,500

£4,800 to £6,600

Side return extension

Single storey rates, plus about 10 per cent

Single storey rates, plus about 10 per cent

Wraparound extension

Single storey rates on the combined floor area

Single storey rates on the combined floor area

Two storey extension

£2,500 to £4,000

£3,000 to £4,800

Loft conversion (rear dormer or hip to gable)

£1,800 to £3,500

£2,160 to £4,200

Basement under the garden

£4,500 to £8,000

£5,400 to £9,600

Basement under the house

Roughly double the garden rate

Roughly double the garden rate

Frameless or high glass extension

£4,500 to £6,000

£5,400 to £7,200

Timber garden studio, general builder

about £1,150

about £1,380

Conservation area

Add about 15 per cent

Add about 15 per cent

Outer boroughs sit at the lower end of each range and inner London at the top. Single storey work in the inner boroughs, such as Camden, Hackney, Islington, Westminster and Kensington and Chelsea, runs higher again, at £4,000 to £5,500 or more, because of tight access, conservation areas and heritage detailing. A side return costs more per metre because of the narrow access, the party wall and the steel along the old flank wall. A hip to gable loft sits higher in its range than a rear dormer, because a new gable wall is built and the roof is reshaped. Two storey work is cheaper per metre because one set of foundations and one roof serve two floors.

New houses are priced from scratch on every job, so they are not in the table.

What does a typical rear extension cost all in?

Take a 25 m² single storey rear extension at mid specification. The build comes to about £75,000 to £87,500 before VAT, which is £90,000 to £105,000 with it. Add £7,000 to £15,000 of pre-build costs and a contingency of 10 to 15 per cent, and the realistic budget sits somewhere around £106,000 to £136,000. That is before the kitchen itself, if you buy it separately.

What is not included in the build price?

These are the costs that come before and around the build, and they are the most common reason a budget runs over. For a typical London extension they come to £7,000 to £15,000 before a brick is laid.

  • Measured survey, about £350 to £700, so the design starts from the house as it really is.

  • Design drawings for planning or a lawful development certificate, about £3,000 to £7,000.

  • Structural engineer's calculations, about £1,000 to £2,000. Every steel beam and foundation needs them.

  • Planning application fee, £548 for householder work in England from April 2026. Check the council's current fee, as the national fees are being revised again from December 2026.

  • Building regulations drawings and building control, about £1,500 to £3,000 for the drawings, inspections and completion certificate.

  • Party wall surveyors, typically £1,000 to £2,000 per adjoining owner, more if a neighbour appoints a surveyor of their own. A semi has one neighbour to serve, a mid terrace usually two.

Then there are the costs during the build that sit outside most quotes. Drainage diversions and moving a manhole, new or upgraded utility connections, skips and parking suspensions, kitchens, bathrooms, flooring and decoration where the builder has priced a shell, and somewhere to live if you need to move out.

Does an extension carry VAT?

Yes. Building work on an extension to an existing house carries VAT at 20 per cent (HMRC VAT Notice 708), and any figure for a build that leaves it out understates the budget by a fifth. Before you compare builders' quotes, check that each one states its VAT position the same way.

There are two exceptions to the 20 per cent rate. Renovating a house that has stood unoccupied for two years or more can be charged at the reduced rate of 5 per cent, provided a VAT registered builder supplies the work and the period can be evidenced, usually from council tax records. Anything you buy yourself, such as the kitchen, still carries 20 per cent. Building a brand new house is zero rated, again through a VAT registered builder, and people building their own house can reclaim the VAT on materials through HMRC's DIY housebuilders scheme. An extension to a house you live in qualifies for neither, so get the position confirmed in writing before you rely on it.

Why do builders' quotes for the same extension differ so much?

Quotes differ because the drawings leave questions open, and each builder answers those questions in their own way. It is quite possible for three honest builders to price the same extension £60,000 apart, because one has assumed the simplest foundations and the cheapest doors, another has allowed for everything they cannot see, and the third plans to sort it out on site.

The cure is to give every builder the same finished package, so a full set of technical drawings, the engineer's design, a schedule of works and a written specification, and then a proper window of four to six weeks to price it. We wrote about this in more detail in our article on why builder quotes differ by £60,000.

Why have extension costs risen so much?

Building costs have risen sharply since 2020. This is Money reported in October 2026, using planning data from PlanningLens across 77 English councils, that applications for single storey extensions fell by 43 per cent between 2021 and 2025. The same piece reported that building materials cost 39 per cent more than before the pandemic, and quoted a surveyor who now allows £50,000 for a loft conversion where he used to allow £25,000. We see the effect in our own enquiries, with more people wanting the number before they commit to drawings.

How do you keep an extension within budget?

Get a written number before the drawings. The most expensive mistake we see is a design that took months to draw and turns out to be far more than the family can spend. Our Stage Zero Review tests your budget against your brief before the full drawings are done, with sketch designs and costed options for your house. It costs £600, including a site visit, and the fee is credited in full if you go ahead with us.

Find out the value ceiling for your street. Every street has a price that houses on it tend to sell for. You can spend beyond it, and plenty of people do because they plan to stay, but it should be a choice you make knowingly. The answer is usually to adjust the extent of the work, so the size, the specification or the order, and very rarely to drop the project.

Phase the work under one design and one consent. This autumn we reviewed a house in outer east London where the brief, priced as written, came to nearly twice the budget. A plainer specification throughout did not come close to closing the gap, because most of the cost sat in the structure, the new shells and the services rather than in the surfaces. What did work was designing the house once, making one planning application, and building a first phase that fits the money now, with the rest to follow under the same consent. Phasing costs a little more overall, as each phase brings its own scaffold and set-up, so allow 5 to 10 per cent on the later phases, and put the heating and electrics in the first phase so they are done once.

Look at the structure and the plan before the finishes. Our own materials research this autumn found the same pattern. Swapping finishes saves little, while choices about the structure and the plan, such as a simpler span or a sensible layout, save real money. There are still some easy wins on materials. The same facing brick was £810 per thousand at one merchant and £2,350 at another, and one leading brand of insulation board cost about twice as much as others with the same thermal performance. A rooflight can do much of what a fully glazed roof does for a fraction of the price.

Combine the work where you can. If the loft or a refurbishment is likely in the next few years, doing it with the extension usually costs less than two separate projects, with one scaffold, one set-up and one period of disruption.

Make the decisions before work starts on site. Changes made on site are the most expensive kind. Keep a contingency of 10 to 15 per cent on the build for what the ground and the old walls reveal, and try not to spend it on changes of mind.

None of this means a plainer house. A well-planned room that gets the light right costs about the same to build as a badly planned one, and good design is a large part of what the money buys. The savings that work are the ones that leave the design intact.

Frequently asked questions

How much does a single storey rear extension cost in London in 2026?

About £2,800 to £4,500 per square metre before VAT, or £3,360 to £5,400 with it, and £4,000 to £5,500 before VAT in inner London. A 25 m² extension at mid specification is around £90,000 to £105,000 including VAT, or about £106,000 to £136,000 once pre-build costs and contingency are added.

Is a loft conversion cheaper than an extension?

Usually, per square metre: about £1,800 to £3,500 before VAT for a loft, against £2,800 to £4,500 for a single storey extension. A loft avoids new foundations and keeps the garden, but needs stairs and often a new gable or dormer, so it depends on the house.

How much contingency should I keep for an extension?

Keep 10 to 15 per cent of the build cost. Older houses and anything below ground sit at the higher end.

Do I pay VAT on a house extension?

Yes, building work on an extension carries VAT at 20 per cent. Renovating a house unoccupied for two years or more can qualify for 5 per cent, and a new house is zero rated, both through a VAT registered builder.

How much does a party wall award cost?

Typically £1,000 to £2,000 per adjoining owner, where the Party Wall Act applies, and more if a neighbour appoints a surveyor of their own. A mid terrace often has two neighbours to serve.

How long does it take to get builders' prices?

Allow four to six weeks for builders to price a full technical package properly. A quote that comes back in two days is usually a guess.

Talk to us about your house

If you want to know what your extension is likely to cost, book a free 30-minute call. Bring your budget and your list, and we will start from there.

About the author

Robert McBride BSc (Hons) MFPWS is the director of Studio : MASS, an architectural technologist and a member of the Faculty of Party Wall Surveyors. The practice has taken more than 300 London homes from first idea to finished build, and prices every project line by line before the drawings are done.

Last updated 20 November 2026. Sources: Studio MASS cost plans and Stage Zero reviews, autumn 2026 (anonymised); Studio MASS London build cost rates 2025 to 26, as published in our borough guides; Studio MASS materials price survey, 26 October 2026; HMRC VAT Notice 708 (buildings and construction); This is Money, 13 October 2026, reporting PlanningLens planning data from 77 English councils.